Stop work order
In the United States, a stop work order (SWO) is a formal notice that can be issued to a contractor by a client compelling them to suspend or cease work. SWOs are typically permitted by all federal contracts as a means of protecting workers, the public, buildings, the surrounding area, the environment, and so on.
Building officials can issue SWOs if inspectors decide that the works are in violation of building codes, zoning ordinances, or any other law or regulation, including health and safety rules.
If an SWO is not subsequently followed with an order to resume work (a start order), it amounts to the contract being terminated.
The following items are typically included in an SWO:
- A description of the activities being suspended (it may only relate to a portion of the works).
- Instructions for the contractor relating to any orders, permits, or services that are pending.
- Instructions about how to manage subcontracts.
- How the contract can be terminated if required.
- How a start order will be issued (what needs to be resolved, how to arrange a re-inspection and so on).
- The penalties that will be imposed if the SWO is not followed.
It is important that all costs are documented and tracked during the SWO process so that they can be reimbursed if appropriate at a later date. The contractor may be entitled to an adjustment or reappraisal of the schedule and contract price if the SWO means that there is an increase in the time and cost of delivering the project.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.